Latest news about the construction

Here you can stay updated on the timeline and construction process – what is happening and when? We will provide regular updates with new information as much as we can.

Follow us on Instagram, where we post the latest updates.

NB!

We look forward to creating a beautiful development, but to be honest – we will make some noise while we build. Naturally, we comply with Frederiksberg Municipality's regulations regarding environmental conditions. This means that the construction site may make noise or create dust on weekdays between 7 AM and 6 PM. We will do everything we can to minimize noise and other inconveniences as much as possible.

Demolition until spring 2025

Updated on January 17, 2025

Demolition
We are in the process of demolishing the extension at Frederiksberg Allé 22, as well as the elevated walkway connecting the two innermost buildings on the site. Following this, we will begin demolishing the extension on the building facing Værnedamsvej. The entire demolition process is expected to take approximately three months from week 3 and is anticipated to be completed before spring arrives.

New secured entrance to the construction site
Additionally, we have begun constructing a secured entrance and exit for the construction site in the form of a gate system at Sankt Thomas Plads, in collaboration with Frederiksberg Kommune and the closest neighbors. This is being done to separate construction site traffic from other road users and to ensure that unauthorized individuals cannot access the site. This is a standard part of any construction process and ensures your safety when passing by the entrance.

January and February 2025

Updated on January 6, 2025

We have completed the interior demolition and geotechnical investigations as planned.

In week 3, the demolition of the extension at Frederiksberg Allé 22 as well as the elevated walkway will begin. The demolition is expected to take approximately three weeks. This work marks the start of the exterior phase of the project, and we look forward to continuing the development with the same focus on quality and the environment.

The next phase of the process is expected to be announced here on the site at the end of February.

Foto af tilbygningen på bygningen ved Frederiksberg Allé 22, Den Franske Skole på Værnedamsvej

The timeline from now and until Christmas 2024

Updated on October 31, 2024

We are currently conducting interior demolition in all three buildings. Additionally, we are carrying out geotechnical investigations in the area. All of this is preparatory work for the actual construction, which is expected to begin in the first half of 2025.

 

Overtagelsesdag

Updated on June 15, 2024

Vi har officielt overtaget ejendommen og begynder i samarbejde med Holscher Nordberg arkitekter at udarbejde planen for projektet.